Instrumentation runs through several PSM elements. Safety systems are part of equipment process safety information under (d)(3)(i)(H), operating procedures must cover safety systems and their functions under (f)(1)(iv), and controls, alarms, interlocks, and emergency shutdown systems are mechanical integrity equipment under (j)(1)(iv) and (v). Under (l)(1), changes to process technology and equipment, other than replacement in kind, go through management of change. OSHA's letters connect those pieces to industry standards for safety instrumented systems.
What OSHA Has Said
Mar 23, 2000
ISA S84.01 and safety instrumented systems under PSM
ISA asked how its SIS standard relates to PSM. OSHA said ANSI/ISA-S84.01 is a national consensus standard it considers RAGAGEP for safety instrumented systems, though not the only one. SIS are process equipment: the employer must document the codes used (d)(3)(i)(F) and RAGAGEP compliance (d)(3)(ii), have operating procedures for safety systems (f)(1)(iv), and inspect and test them under mechanical integrity (j). The employer is responsible for deciding whether an SIS is needed. An employer that documents and meets S84.01 and the other PSM requirements for SIS is considered in compliance.
Read OSHA Letter ↗
Nov 29, 2005
The 2004 edition of ISA 84
OSHA recognized ANSI/ISA-84.00.01-2004, the updated edition of the SIS standard, as a recognized and generally accepted good engineering practice for safety instrumented systems.
Read OSHA Letter ↗
Dec 7, 1995
Which instruments belong in mechanical integrity
Union Carbide asked about the MI equipment list in (j)(1). OSHA said employers may add equipment they consider critical to the list, and that ISA S91.01, which identifies emergency shutdown systems and controls critical to safety, can be used as guidance in deciding which instruments to include.
Read OSHA Letter ↗
Oct 31, 1996
Changing test frequencies is a change
OSHA said that, except for replacements in kind, management of change applies to changes in maintenance procedures and in equipment test and inspection frequencies, so lengthening a proof-test interval on a safety instrument is a change that needs MOC.
Read OSHA Letter ↗
⚡ Key Compliance Takeaway
Document which SIS standard you follow and show your safety instrumented functions meet it. Put critical instruments, alarms, and interlocks on your MI list with defined test intervals, and run setpoint changes, bypasses, logic changes, and test-interval changes through MOC. Only a like-for-like instrument that satisfies the design specification skips MOC.